- 12-1 Using the information in Table 12-7, construct a PERT network and answer each of the following questions:
- a. What is the expected project completion data?
- b. What is the scheduled start and completion date for each activity?
- c. Which activities are on the critical path?
- d. How long can noncritical path activities be delayed without jeopardizing the overall completion date for this project?
- 12-2 Assess the impact of the following changes to the time estimates provided in question 12-1. Individually, what is the impact if:
Activity | Predecessor | New Time Estimate |
O. Advertise for new staff | N | 4 |
P. Interview for new staff | O | 6 |
Q. Select new staff | P | 1 |
Collectively, what is the impact of these changes? |
- 12-3 As project manager for the example included in question 12-1, what would you recommend to preserve the original project completion date if activity A was reestimated to take 8 weeks, not the original 4 weeks? Provide details.
·
· Table 12-7 Project to Convert a 20-Bed Unit in a Nursing Home to Accommodate Patients with Dementia
Activity | Predecessor | Time estimate (weeks) | |
A | Secure state approval | – | 4 |
B | Identify 20-bed unit to be used | A | 1 |
C | Move existing residents | B | 1 |
D | Clean space | C | 2 |
E | Develop architectural plans | A | 9 |
F | Install new heating and ventilation systems | E | 4 |
G | Install security systems | E | 2 |
H | Move walls; renovate | F | 4 |
I | Identify new equipment | A | 1 |
J | Order new equipment | I | 1 |
K | Unpack and inspect new equipment | J | 1 |
L | Install new equipment | D, K, H | 3 |
M | Reassign staff | A | 1 |
N | Identify new staffing needs | M | 1 |
O | Advertise for new staff | N | 3 |
P | Interview for new staff | O | 2 |
Q | Select new hires | P | 3 |
R | Develop care plan protocols | M | 1 |
S | Train staff | R, Q, M, L | 1 |
T | Modify quality assurance plans | S | 2 |
U | Coordinate with hospital discharge planners | T | 4 |
V | Complete internal audit | U, G | 1 |